Ohio Eastern Star Health Care Center, Inc.
Survey Date: Tuesday, April 8, 2014
Survey Type: Fire Safety
Deficiency: K0018 (Corridor and hallway doors that block smoke.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, May 23, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Tuesday, April 8, 2014
Survey Type: Fire Safety
Deficiency: K0144 (Weekly inspections and monthly testing of generators.)
Scope Severity Code: C
Deficiency Corrected: Deficient, Provider Has Plan Of Correction
Date the deficiency was corrected: Friday, May 23, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, April 3, 2014
Survey Type: Health
Deficiency: F0309 (Provide necessary care and services to maintain or improve the highest well being of each resident .)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, May 23, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, April 3, 2014
Survey Type: Health
Deficiency: F0279 (Develop a complete care plan that meets all the resident's needs, with timetables and actions that c)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, May 23, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, April 3, 2014
Survey Type: Health
Deficiency: F0441 (Have a program that investigates, controls and keeps infection from spreading.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, May 23, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, April 3, 2014
Survey Type: Health
Deficiency: F0323 (Ensure that a nursing home area is free from accident hazards and provide adequate supervision to pr)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, May 23, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Wednesday, January 23, 2013
Survey Type: Fire Safety
Deficiency: K0147 (Properly installed electrical wiring and equipment.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Saturday, March 9, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Wednesday, January 23, 2013
Survey Type: Fire Safety
Deficiency: K0051 (A fire alarm system that can be heard throughout the facility.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Saturday, March 9, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Wednesday, January 23, 2013
Survey Type: Fire Safety
Deficiency: K0038 (Exits that are accessible at all times.)
Scope Severity Code: F
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Saturday, March 9, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Wednesday, January 23, 2013
Survey Type: Fire Safety
Deficiency: K0018 (Corridor and hallway doors that block smoke.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Saturday, March 9, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Friday, January 18, 2013
Survey Type: Health
Deficiency: F0159 (Properly hold, secure, and manage each resident's personal money which is deposited with the nursing)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Saturday, March 9, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Friday, January 18, 2013
Survey Type: Health
Deficiency: F0272 (Conduct initial and periodic assessments of each resident's functional capacity.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Saturday, March 9, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Friday, January 18, 2013
Survey Type: Health
Deficiency: F0329 (Ensure that each resident's 1) entire drug/medication regimen is free from unnecessary drugs; and 2))
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Saturday, March 9, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Friday, January 18, 2013
Survey Type: Health
Deficiency: F0425 (Provide routine and emergency drugs through a licensed pharmacist and only under the general supervi)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Saturday, March 9, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Friday, January 18, 2013
Survey Type: Health
Deficiency: F0496 (1) Receive registry verification that a nurse aide has met the required training and skills that the)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Saturday, March 9, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, September 22, 2011
Survey Type: Health
Deficiency: F0279 (Develop a complete care plan that meets all the resident's needs, with timetables and actions that c)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, November 11, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Thursday, September 22, 2011
Survey Type: Health
Deficiency: F0157 (Immediately tell the resident, the resident's doctor, and a family member of situations (injury/decl)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, November 11, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Thursday, September 22, 2011
Survey Type: Health
Deficiency: F0329 (Ensure that each resident's 1) entire drug/medication regimen is free from unnecessary drugs; and 2))
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, November 11, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Thursday, September 22, 2011
Survey Type: Health
Deficiency: F0514 (Keep accurate, complete and organized clinical records on each resident that meet professional stand)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, November 11, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Wednesday, September 21, 2011
Survey Type: Fire Safety
Deficiency: K0038 (Exits that are accessible at all times.)
Scope Severity Code: F
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, November 11, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Wednesday, September 21, 2011
Survey Type: Fire Safety
Deficiency: K0018 (Corridor and hallway doors that block smoke.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, November 11, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Wednesday, September 21, 2011
Survey Type: Fire Safety
Deficiency: K0073 (Restrictions on the use of highly flammable decorations.)
Scope Severity Code: F
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Friday, November 11, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)